Tough Patch Rapid 6mm Pothole Repair Solution
Tough Patch Rapid is a super strong, hard wearing, fast setting, hybrid pothole repair solution that withstands extreme traffic due to its high skid and rut resistance. Quick and easy to install, Tough Patch Rapid pothole repair can be used to fix defects in pavements, driveways, car parks and on high speed roads. Tough Patch provides a first time permanent repair in wheel turning locations such as junctions, traffic lights and roundabouts.
UltraCrete Tough Patch uses an innovative reactive binder that rapidly cures to provide a first time permanent repair, this binder is based on renewable materials and contains no solvents. The rapid curing reaction is activated by sprinkling water over the product before compacting. Once compacted the installation can be instantly opened to traffic and is able to be cored for assessment after 24 hours. The product can be used in all weather conditions. Tough Patch 6mm can also be used for emergency or temporary repairs where a rapid response is required to prevent risk to operatives, pedestrians, cyclists and motorists
Tough Patch comes supplied in a 25KG tub and is ready to use straight out of the bucket, because it’s a cold lay material it eliminates many of the risks associated with hot asphalt, such as extremely hot temperatures and dangerous fumes, and what’s more it can be trafficked instantly and used in the rain – so costly traffic management can be removed swiftly and you can move on to your next job quickly.
Use in conjunction with UltraCrete’s HAPAS approved SCJ Seal and Tack Coat spray and Instaband ECO overbanding for a complete reinstatement system which can save you vital time and money!
How to prepare and apply UltraCrete Tough Patch
- Permanent repairs require best practice in saw cutting around the defect or opening to ensure straight, vertical edges that support compaction of material when installed.
- Remove any debris, mud, silt or ice from within the defect.
- To enhance the longevity of the repair, seal the vertical cut edges and base of asphalt defect or opening with Ultracrete SCJ Seal & Tack. This is essential when the substrate is concrete.
- Apply Tough Patch from the bag or bucket using the layer method (see below) which ensures uniform compaction and longevity of repair.
- Loosely spread each layer uniformly into the defect or opening using a shovel or rake.
- Before compacting each layer, sprinkle water over the complete surface at the approximate ratio of 1litre per 25kg bag of Tough Patch – this will activate the curing process.
- Mechanically compact the material in accordance with Appendix 8 of the SROH and repeat the process for all layers ensuring the material final layer is slightly proud of the surrounding area and fully compacted.
How to apply Tough Patch for emergency repairs
For emergency repairs, saw cutting (step 1) and thorough cleaning (step 2) may not be able to be fully undertaken due to traffic management requirements, therefore the material can be used in an emergency or in reactive maintenance programmes to prevent pedestrian, vehicle or cycle harm or damage, with the knowledge that a more permanent solution can be carried out at a later date.
During an emergency repair the pothole may be filled in one application. Compact using a suitable tamping device or in areas where there is limited traffic management in place, allow traffic to compact.
It is the responsibility of the user to satisfy themselves on the effectiveness of the application.
Layer installation method for Tough Patch
Tough Patch 6mm for paving is generally installed at a max 60mm depth in accordance with SROH. This is applied in layers as follows:
- Apply product to a depth of 45mm and compact to 30mm for first layer
- Repeat process to achieve a total 60mm finished depth.